The most appropriate sequencing rule to use if the goal is to dynamically track the progress of jobs and establish relative priority on a common basis is
A) shortest processing time
B) earliest due date
C) critical ratio
D) longest processing time
E) Johnson's rule
Correct Answer:

Verified
Correct Answer:
Verified