Essay
The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants -- Charlie, Gerald, Johnny, and Rick -- to complete any of the four projects, as follows:
a. In how many different ways can she assign these consultants to these projects?
b. What is the total number of hours required by the following arbitrary assignment?
Charlie→B; Gerald→A; Johnny→D; Rick→C
c. What is the optimal assignment of consultants to projects?
(Use the assignment method; SHOW YOUR WORK!)
d. For the optimal schedule, what is the total number of hours it will take these consultants to complete these projects?
e. What is the significance, if any, of the fact that Gerald is the best performer at all four projects?
Correct Answer:

Verified
(a) 4!, or 24 ways. (b) 16+13+15+12=56 h...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q28: What does Johnson's rule do?
Q106: _ scheduling begins with the due date
Q118: Which of the following files tracks work
Q119: Eight jobs have been sequenced at a
Q120: Which file contains important information regarding an
Q121: The following jobs are waiting to
Q122: Which of the following are limitations of
Q124: Five jobs are waiting for processing
Q126: An appliance manufacturer assembles icemakers in large
Q127: In repetitive manufacturing, what are the advantages