Solved

At Morgan's Transformer Rebuilding, a Set of Five Jobs Is

Question 23

Essay

At Morgan's Transformer Rebuilding, a set of five jobs is ready for dispatching to a machine center. The processing times and due dates for the jobs are given in the table below. Use shortest processing time to sequence the jobs, and calculate the average completion time, the average job lateness, and the average number of jobs in the machine center.
 Job  Work Time (days)  Due Date (days)  A 1538 B 1328 C 720 D 1850 E 915\begin{array} { | c | c | c | } \hline \text { Job } & \text { Work Time (days) } & \text { Due Date (days) } \\\hline \text { A } & 15 & 38 \\\hline \text { B } & 13 & 28 \\\hline \text { C } & 7 & 20 \\\hline \text { D } & 18 & 50 \\\hline \text { E } & 9 & 15 \\\hline\end{array}

Correct Answer:

verifed

Verified

The optimal sequence is C-E-B-A-D. The a...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions