Multiple Choice
The cook in a fast-food restaurant knows that 2 hamburger patties and an order of fries should be started for each car that is waiting in line. This is best an example of
A) Lead time
B) Kanban
C) Push production
D) Kaizen
E) EOQ
Correct Answer:

Verified
Correct Answer:
Verified