Essay
You have read that in JIT and lean production the optimum lot size is one, with some exceptions for packaging and physical limitations. If a product currently has a lot size of 25, what must happen to setup time for the lot size to truly fall to one?
Data for this problem are D=100 units, S=$75 based on setup time of 50 minutes at $1.50 per minute, and H=$40 per unit per year.
Correct Answer:

Verified
Students may try ever smaller values for...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q15: When suppliers are encouraged to locate near
Q29: Weekly usage of a product is 8
Q68: Variability in manufacturing can occur because engineering
Q80: Which one of the following is a
Q81: Which one of the following is a
Q82: Level scheduling means producing at a constant
Q83: Which of the following is specifically characterized
Q84: Which of the following is not a
Q87: When implemented as a comprehensive manufacturing strategy,
Q90: Identify sources of variability.