A Production Line Is to Be Designed for a Job

Question 88

Multiple Choice

A production line is to be designed for a job with three tasks. The task times are .3 minutes, 1.4 minutes, and .7 minutes. For a single production line with no parallel activities, the minimum cycle time in minutes is:


A)  .3.
B)  .7.
C)  1.4.
D)  2.4.
E)  .8.