Multiple Choice
A manager is trying to estimate the learning rate for a new job. The first unit took 16 hours and the fourth unit required about 13 hours. The learning rate is:
A) 70 percent.
B) 75 percent.
C) 80 percent.
D) 85 percent.
E) 90 percent.
Correct Answer: