A company is preparing a bid on a government contract for 40 units of a certain product. The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours.Which unit, if any, will require approximately one-half the time of the first unit?
A) 18th unit
B) 19th unit
C) 20th unit
D) 21st unit
E) 22nd unit
Correct Answer: