Multiple Choice
In a(n) ________,a manager uses three time estimates: an optimistic,a pessimistic,and a most likely time for completion of each activity.
A) data flow diagram
B) PERT diagram
C) GDSS
D) Gantt chart
Correct Answer:

Verified