Which of the Following Is Absolutely Necessary for Successful Implementation

Question 32

Multiple Choice

Which of the following is absolutely necessary for successful implementation and operation of MRP?
(I) accurate inventory records
(II) master schedules
(III) accurate holding and backordering costs
(IV) accurate bills of materials


A) I, II, and IV only
B) I, III, and IV only
C) I, II, and III only
D) I and II only
E) I, II, III, and IV