Scheduled receipts differ from planned receipts in that scheduled receipts:
A) have longer lead times.
B) involve orders that have not yet been placed.
C) have not been pegged with actual customer orders.
D) involve orders that have already been placeD.
E) involve exceptions to order quantity policies.