Multiple Choice
A scheduling technique used to achieve an optimum matching of tasks and resources is:
A) the assignment methoD.
B) Johnson's rule.
C) the optimum production technology method.
D) the appointment method.
E) the reservation method.
Correct Answer:

Verified
Correct Answer:
Verified