Multiple Choice
Why did the court find that the contract was frustrated in the case of: Codelfa Construction Pty Ltd v State Rail Authority (NSW) (1982) 149 CLR 337?
A) Due to the declaration of war and the consequent impossibility of performing the contract.
B) Due to the non-occurrence of an event essential to achieve the substantial purpose of the contract.
C) Due to the fundamental and radical change in the circumstances of the contract.
D) Due to the complete destruction of the subject matter of the contract.
Correct Answer:

Verified