Multiple Choice
If an organization's requirements conflict with the software package chosen and the package cannot be customized, the organization should:
A) change its procedures.
B) outsource the development of the system.
C) redesign the RFP.
D) change the evaluation process.
Correct Answer:

Verified
Correct Answer: