    A ________ Shows Each Task as a Horizontal Bar Whose
Solved

A ________ Shows Each Task as a Horizontal Bar Whose

Question 40

Question 40

Multiple Choice

A ________ shows each task as a horizontal bar whose length is proportional to the time required to complete it.


A) PERT chart
B) DFD
C) feasibility study
D) Gantt chart

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q8: In an object-oriented development framework for a

Q17: What qualities of object-oriented development make this

Q18: Prototyping is more iterative than the conventional

Q22: Discuss the role and influence the user

Q35: The project risk will rise if the

Q37: You would expect to find all of

Q38: Which of the following is a technique

Q39: _ are tangible benefits of information systems.<br>A)Improved

Q43: Which of the following tools may help

Q45: An entire information system is broken down

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines