Multiple Choice
An organization planned to use $44 of material per unit of activity but it actually used $42 of material per unit of activity,and it planned to make 1,200 units but it actually made 1,000 units.The flexible budget amount for materials is:
A) $42,000.
B) $44,000.
C) $48,000.
D) $49,400.
Correct Answer:

Verified
Correct Answer:
Verified