Which of the following is NOT a requirement for an effective control system?
A) It should be flexible enough to cope with unanticipated changing patterns and problems.
B) It should not be changed in any way after it is adopted until it is abandoned.
C) It should expose deviations as they occur and indicate who is responsible for the deviation.
D) It should be suitable for the activity to be observed.
Correct Answer:

Verified
Correct Answer:
Verified