True/False
If the auditor concludes that the CUER is 5% at a 8% sampling risk, this means that the exception rate in the population is no greater than 5% with an 8% risk of the exception rate exceeding 5%.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q11: It is equally acceptable under professional auditing
Q61: The acceptable risk of overreliance<br>A) is the
Q74: Attributes sampling is based on the _
Q93: Which of the following statements best expresses
Q95: In the evaluation of the results of
Q101: You are designing the audit plan for
Q102: When the computed upper exception rate is
Q130: When the auditor goes through a population
Q143: What types of exceptions are auditors most
Q150: Place the following steps in their proper