A Project-Management Tool That Illustrates the Relationships Among All the Activities

Question 17

Multiple Choice

A project-management tool that illustrates the relationships among all the activities involved in completing a project and identifies the sequence of activities likely to take the longest to complete is called _____.


A) a fixed position layout
B) the critical path method
C) an immediate predecessor
D) a value chain

Correct Answer: