Jorgen Inc., an oil company, is building a large drilling machine close to the site of its latest project to dig an underground tunnel. Since the machine will be big, it is unlikely to be used after this project. A__________should be used to produce the drilling machine.


A) product layout
B) process layout
C) fixed position layout
D) cellular technology layout