Multiple Choice
When does the lead time in a procurement process come to an end?
A) when an order arrives at the warehouse
B) when an invoice is received from the supplier
C) when ordered goods are reflected in the purchase order database
D) when an order is placed with a supplier
Correct Answer:

Verified
Correct Answer:
Verified