Which of the Following Is Not a Sub-Process Associated with Risk

Question 66

Multiple Choice

Which of the following is not a sub-process associated with risk management?


A) risk identification
B) risk measurement
C) qualitative risk analysis
D) quantitative risk analysis
E) risk response planning

Correct Answer: