Multiple Choice
What is the expected time to complete a task with an optimistic, most likely, and pessimistic times of 3, 4, and 7 days respectively?
A) 3
B) 4
C) 4.3
D) 4.7
E) 7
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q60: Consider a project network that begins with
Q61: Technical dependencies are generally easier to see
Q62: Why should we only draw the Gantt
Q63: The scum master develops estimates for the
Q64: The actual project duration will be known
Q66: An identifiable state resulting from the completion
Q67: An Agile team's velocity is only valid
Q68: Activities on a project always meet the
Q69: PERT was originally used for what type
Q70: The formula for the expected time of