What is the expected time to complete a task with an optimistic, most likely, and pessimistic times of 3, 4, and 7 days respectively?


A) 3
B) 4
C) 4.3
D) 4.7
E) 7

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q60: Consider a project network that begins with

Q61: Technical dependencies are generally easier to see

Q62: Why should we only draw the Gantt

Q63: The scum master develops estimates for the

Q64: The actual project duration will be known

Q66: An identifiable state resulting from the completion

Q67: An Agile team's velocity is only valid

Q68: Activities on a project always meet the

Q69: PERT was originally used for what type

Q70: The formula for the expected time of

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines