Multiple Choice
To crash a project, which of the following principles apply? 1) Focus on the critical path(s) when trying to shorten the duration of a project, 2) Select the least expensive way to do it 3) Crash non-critical activities
A) All three are correct
B) Only 1 and 3 are correct
C) Only 1 and 2 are correct
D) Only 1 is correct
Correct Answer:

Verified
Correct Answer:
Verified