Multiple Choice
Which of the following was not mentioned in the text as a valuable source of information for a project audit?
A) the project's Request for Proposal
B) minutes from the project selection committee
C) benchmark data from other similar projects
D) minutes of senior management committees that initiated the project
E) All of the above were mentioned in the text as valuable sources of information for a project audit.
Correct Answer:

Verified
Correct Answer:
Verified