The Critical Path Method Is a Project Management Tool That

Question 61

True/False

The Critical Path Method is a project management tool that illustrates the relationships among the activities involved in completing a project and enables managers to identify those activities that are most likely to create delays in the completion of the overall project.

Correct Answer: