In Project Scheduling Terminology,activities That Must Be Completed Before Other

Question 81

Multiple Choice

In project scheduling terminology,activities that must be completed before other activities can begin are referred to as which of the following?


A) schematics
B) temporal priorities
C) immediate predecessors
D) critical activities

Correct Answer: