Which of the Following Is a Project Management Tool Illustrating

Question 91

Multiple Choice

Which of the following is a project management tool illustrating relationships among all activities involved in completing a project,thus enabling managers to identify activities that are most likely to delay the project's completion?


A) an activity interdependence reference table
B) the Critical Path Method
C) a value stream map
D) an activity inventory network table