Paolo Brothers Inc.has been awarded a contract to build the new middle school for a local school district.Jim Paolo,a project manager for the company,has put together a list of activities necessary to complete the project,the time it will take to complete each activity,and each activity's immediate predecessors.This information could be used to construct which of the following?


A) a Venn diagram
B) a building specification chart
C) a critical path network
D) an activity time flow matrix