Multiple Choice
A project
A) is a temporary endeavor undertaken to accomplish a unique product, service, or result.
B) is an ongoing activity that provides value to the organization.
C) must be completed on time and on budget to be successful.
D) does not usually have a deadline.
E) has a high likelihood of success.
Correct Answer: