Monitoring and controlling processes:


A) Signal the beginning of the project or phase.
B) Requires an organization to make a commitment of time and resources.
C) focus on integrating people and resources to carry out the planned activities.
D) supports planning of the entire project and each individual phase
E) allows for managing and measuring progress toward the project's MOV and scope, schedule, budget, and quality objectives.