Multiple Choice
Which of the following statements is the best indicator that the new software project was successful.
A) The project's product, a software system, was enthusiastically accepted by 100% of the end users who were able to begin using it after completing only a one-day training session.
B) The project's product, a software system, was a week late and 2% over budget, but six months later was found to have met the company's goal of reducing service callbacks by 15%.
C) The project's product, a software system, was completed two weeks ahead of time freeing up the entire development team to begin work on other projects.
D) The project's product, a software system, was completed right on schedule and was delivered $10,000 under the $100,000 budget allocation.
E) The project's product, a software system, was completed on time and on budget and was tested and shown to be 100% bug-free.
Correct Answer:

Verified
Correct Answer:
Verified
Q5: Evaluating the feasibility of an alternative in
Q15: Which of the following was NOT given
Q17: <b>Why must stakeholders agree on the project's
Q18: The MOV should be adjusted at each
Q19: A project that increased profits would impact
Q21: <b>Describe how a project's MOV can support
Q22: <b>What is economic feasibility?</b>
Q23: Determining whether the proposed solution will work
Q24: Which of the following is the best
Q25: <b>What is Total Cost of Ownership?</b>