    A Communication Plan, a Quality Management Plan, and Change Management
Solved

A Communication Plan, a Quality Management Plan, and Change Management

Question 21

Question 21

Multiple Choice

A communication plan, a quality management plan, and change management plan are all associated with which part of the project charter?


A) Project Resources
B) Project Scope
C) Project Description
D) Project References
E) Project Administration

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q16: What is a project environment and how

Q17: Clear authority and responsibility, improved communication, and

Q18: Describe the roles of a project manager.

Q19: What is meant by the formal organization?

Q20: The project charter<br>A) and the project plan

Q22: Describe the functional organizational structure.

Q23: _ integrates areas and resources throughout the

Q24: The main feature of the Matrix Organizational

Q25: Describe the project governance structure.

Q26: Disadvantages of the Project Organizational structure include

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines