Multiple Choice
The _____ describes how changes to the project's scope will be submitted, logged, and reviewed.
A) Communications Plan
B) Scope Management Plan
C) Quality Management Plan
D) Change Management Plan
E) Human Resources Plan
Correct Answer:

Verified
Correct Answer:
Verified