Multiple Choice
Which of the following statements about the work breakdown structure (WBS) is not true?
A) The WBS provides a hierarchical structure that outlines the activities or work that needs to be done in order to complete the project scope.
B) The WBS should support the project's MOV
C) The WBS should be developed by the project manager.
D) The WBS provides a framework for developing a tactical plan to structure the project work.
E) The WBS provides a bridge or link between the project's scope and the detailed project plan
Correct Answer:

Verified
Correct Answer:
Verified
Q44: _ may result in long hours and
Q45: What is time boxing? What are some
Q46: What defines what will be, and will
Q47: Scope change control procedures protect the scope
Q48: Time boxing involves allocating a time segment
Q50: _ can be very effective and provide
Q51: Product scope is a statement detailing the
Q52: The concept of actors is an integral
Q53: Why is important to ensure that the
Q54: Describe product-oriented scope and the tools that