menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Information Technology Project Management Study Set 1
  4. Exam
    Exam 6: The Work Breakdown Structure and Project Estimation
  5. Question
    Identifying the Critical Path Is Important Because Any Change in the Duration
Solved

Identifying the Critical Path Is Important Because Any Change in the Duration

Question 50

Question 50

True/False

Identifying the critical path is important because any change in the duration of the activities or tasks on the critical path will affect the project's schedule.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q45: The critical path has zero slack (or

Q46: The amount of time an activity can

Q47: Define predecessor, successor, and parallel activities.Give a

Q48: An over allocated resource would arise when

Q49: Parallel activities can shorten the project schedule,

Q51: Starting the next task before the first

Q52: Completing activities in parallel is called_<br>A) slacking.<br>B)

Q53: Costs incurred prior to the current project

Q54: Describe the steps necessary for estimating the

Q55: Scheduling other projects so that resources may

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines