Multiple Choice
The Critical Path is:
A) the longest path in the project network.
B) the shortest path in the project network.
C) the longest time in which the project can be completed.
D) the interrelationships of project activities.
E) the most important identified tasks within the project.
Correct Answer:

Verified
Correct Answer:
Verified