If you hired a consulting firm to develop a system which is estimated to take four months to complete with the tasks evenly divided over the four months and you agree to pay for the project with equal monthly installments, those payments would be called:
A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Earned Value (EV)