Multiple Choice
Which of the following is a product-oriented activity that attempts to determine if the system or project deliverable meets the customer or client's expectations?
A) Verification
B) Validation
C) Configuration management
D) Fact-based management
E) Software process maturity
Correct Answer:

Verified
Correct Answer:
Verified