Multiple Choice
The most important requirement for project closure under normal circumstances is:
A) completing the project on time.
B) completing the project on or under budget.
C) redeploying team members successfully to other projects.
D) following the project methodology.
E) obtaining the project sponsor's acceptance of the project.
Correct Answer:

Verified
Correct Answer:
Verified