Solved

The Most Important Requirement for Project Closure Under Normal Circumstances

Question 48

Multiple Choice

The most important requirement for project closure under normal circumstances is:


A) completing the project on time.
B) completing the project on or under budget.
C) redeploying team members successfully to other projects.
D) following the project methodology.
E) obtaining the project sponsor's acceptance of the project.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions