  5. Question
    In___________ ,The Old System Is Used Along with the New
Solved

In___________ ,The Old System Is Used Along with the New

Question 40

Question 40

Multiple Choice

In___________ ,the old system is used along with the new system for a predetermined period of time.


A) phased conversion
B) cut-over conversion
C) parallel conversion
D) flash cut conversion

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q35: _is a set of processes and methods

Q36: Legacy systems are older systems that organizations

Q37: When planning,it is important to align IT

Q38: A carefully drawn_ can provide a useful

Q39: _is a graphical standard for visualizing,specifying,and documenting

Q41: The systematic approach of the SDLC is

Q42: _consists of post-implementation debugging and updating (making

Q43: When a system is developed by a

Q44: After the planning phase,the SDLC includes four

Q45: How is parallel conversion implemented?

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines