Multiple Choice
Jessica hires ChromaLite Builders Corp.to construct a house.The contract specifies that grade A+ carpeting is to be installed on the entire second floor.ChromaLite Builders accidentally installs grade A carpeting instead.Few people,except for carpeting experts,can tell the difference.Jessica,however,refuses to pay for the construction citing that ChromaLite Builders has breached the contract.Which of the following statements is true in this scenario?
A) The courts are likely to consider ChromaLite Builders's performance as complete performance, and Jessica will have to pay the full amount to ChromaLite Builders.
B) Jessica can claim a breach of contract and refuse to pay ChromaLite Builders for the construction of the house.
C) The courts are likely to consider ChromaLite Builders's performance as a substantial performance, and Jessica would be entitled to monetary damages.
D) Jessica has materially breached the contract by refusing to pay ChromaLite Builders; hence, she cannot sue ChromaLite Builders for the use of low-grade carpeting.
E) The courts are likely to declare that ChromaLite Builders has materially breached the contract and will ask Jessica to pay exactly half the cost originally mentioned in the contract.
Correct Answer:

Verified
Correct Answer:
Verified
Q18: In the context of levels of performance,substantial
Q19: An exception to the parol evidence rule
Q20: A party that has materially breached a
Q21: ToughBuilders Corp.,a construction company,finishes the construction of
Q22: The meaning of a contract is a
Q24: Jeff signs a contract agreeing to purchase
Q25: The purposeful reduction of damages,usually the responsibility
Q26: What is an injunction?
Q27: When a contract involves unique subject matter,courts
Q28: What is the theory behind awarding money