Multiple Choice
Daniel's failure to deliver ice-cream makers and waffle makers on time resulted in a two-week delay in the opening of Sheena's new ice-cream parlor.Sheena incurred a heavy loss since she had to pay the rent for those two weeks as well as salaries to the personnel hired.In this case,which of the following remedies is a court most likely to award Sheena?
A) liquidated damages
B) consequential damages
C) nominal damages
D) specific performance
E) differential damages
Correct Answer:

Verified
Correct Answer:
Verified
Q60: Most of our everyday purchases involve _
Q61: Rachel contracted with Steven to cater her
Q62: Complete performance recognizes that a contracting party
Q63: How is specific performance used as an
Q64: When a printed form contract has additional
Q66: What are the options available to nonbreaching
Q67: Faiza hired Bril Builders Inc.to construct her
Q68: _ is a middle ground between full
Q69: Oral evidence that changes the meaning of
Q70: Which of the following statements is true