True/False
As a rule of thumb,the lowest level tasks in a typical project should NOT take longer than two days to complete.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q18: RACI stands for remove all cost information.
Q18: 43 In order to prepare a mind
Q19: Defining resource needs is NOT necessary on
Q23: Lack of planning is a major contributor
Q24: What is the primary purpose of creating
Q26: The Design Structure Matrix can be used
Q39: Mind mapping is a whole-brain approach that
Q43: Predecessors must be listed in the WBS
Q54: SMT standards for<br>A) staff, management, and technicians<br>B)
Q68: The start and finish date of a