Multiple Choice
Entries above the diagonal in the Design Structure Matrix indicate
A) tasks that need to be shortened
B) tasks that have no resources assigned to them
C) tasks that are on the critical path
D) potential rework situations
E) tasks with no predecessors
Correct Answer:

Verified
Correct Answer:
Verified