A Problem with Bottom-Up Budgeting Is

Question 51

Multiple Choice

A problem with bottom-up budgeting is:


A) individual team members overstate their budget needs
B) lack of involvement from the project team
C) underestimating the project task's budget requirements
D) all of the above
E) none of the above