    The Formula for the Expected Time of an Activity in a Network
Solved

The Formula for the Expected Time of an Activity in a Network

Question 35

Question 35

True/False

The formula for the expected time of an activity in a network assumes that the optimistic, pessimistic, and most likely time estimates have a Beta distribution.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q6: A diagram of nodes connected by directional

Q8: What assumptions are made about the probabilities

Q17: Rico Gen, a sports apparel manufacturing company,

Q22: When it was originally developed, PERT used

Q25: Networks are usually drawn with a "Start"

Q43: What is activity slack?

Q55: AON and AOA networks can both be

Q58: Ben is part of a new project

Q82: If task duration estimates are carefully made,

Q108: Contrast total slack and free slack.

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines