Multiple Choice
For which purpose is simulation NOT used with regard to project scheduling?
A) to overcome the limitations associated with statistical techniques used to develop probability of completion time estimates
B) to investigate the range of project completion times
C) to investigate the distribution of project completion times
D) to verify the accuracy of the optimistic, pessimistic and most likely time estimates
E) all of the above