Multiple Choice

Which of the following is typically used as the best estimate of task duration?


A) expected time
B) pessimistic time
C) optimistic time
D) most likely time
E) none of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q13: A start-to-finish linkage is the most common

Q27: Slack is calculated as?<br>A) LFT - EST<br>B)

Q35: The formula for the expected time of

Q38: The simulation approach is generally preferred over

Q40: What are the four methods of linking

Q47: Which of the following terms is most

Q53: Events in a project consume no resources

Q63: Milestones cannot be identified on a Gantt

Q75: Technical dependencies are often harder to see

Q78: Another name for total slack is free

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines