The amount of time a noncritical task can be delayed without delaying the project is called?


A) surplus
B) flop
C) slack
D) critical time
E) safety

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q83: Formula for the expected completion time of

Q84: Why is it necessary for the project

Q85: "Merger" is a term used to describe

Q86: A Gantt chart cannot depict a critical

Q87: An activity using slack does not impact

Q89: High velocity is a goal of Agile

Q90: A Term not used in the discussion

Q91: An approximation of the variance for an

Q92: The amount of time an activity can

Q93: A situation where two or more activities

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines